Renovating in Monaco.

Working hours, truces, permits, co-ownership, logistics: the essentials before starting works in the Principality — and how we build them into every project.

01

The worksite calendar

To preserve residents’ peace and quiet, the Principality strictly regulates worksites. Since 2019, works have been allowed from Monday to Friday, during the day: on Saturdays and Sundays, sites stand still.

Two truces apply every year: from 24 December to 1 January, and in August, when only quiet interior works are allowed.

Works outside these hours are accepted only exceptionally, for technical reasons.

  1. J
  2. F
  3. M
  4. A
  5. M
  6. J
  7. J
  8. A
  9. S
  10. O
  11. N
  12. D
Works allowed (Mon–Fri) Quiet interior works only Truce (24.12 – 01.01)

Our advice: schedule the noisy phases (demolition, core drilling, screeds) outside August, and plan around the year-end truce if you want to move in before the holidays.

02

Permits

Works that change a building’s interior layout or exterior appearance require prior authorisation from the Department of Forward Studies, Urban Planning and Mobility (DPUM).

The application is signed by an architect registered with the Monaco Order of Architects, by the owner and by the building manager. For interior works, the administration has 45 days from the filing of a complete application. On completion, a compliance inspection is requested from the DPUM within the following month.

Renovations without structural changes — painting, flooring, replacing a kitchen or a bathroom — generally do not require a permit; the building manager must nevertheless be informed.

Subject to authorisation

  • Creating or enlarging openings
  • Work on load-bearing walls
  • Full-height partitions, new service shafts
  • Change of use (residential, office, retail)
  • Changes to the exterior appearance
03

Co-ownership

Building regulations often set their own rules: hours, use of lifts, protection of common areas, deliveries. Some works must be put to a vote at the general meeting.

We take care of protecting common areas, coordinating with the building manager and concierge, and keeping access areas clean every day.

04

Monaco logistics

Narrow streets, scarce parking, high-rise buildings: deliveries and debris removal must be prepared. Occupying the public road — skips, scaffolding, material hoists — requires authorisation.

We organise deliveries, storage and removals at the pace of the works, keeping disturbance to the neighbourhood to a minimum.

05

Authorised companies

In Monaco, carrying out a business activity requires authorisation: a foreign company cannot work without specific approval and the declaration of its employees.

EGB is a Monegasque public limited company (S.A.M.), registered with the Trade and Industry Register under no. 10S05232.

06

Plan your works

Enter your start month and the expected duration: we calculate a handover date that accounts for weekends, Monaco public holidays and the truces.

Estimated handover

early April 2027

Start December 2026

  • The schedule spans the year-end truce.

Weekends, Monaco public holidays and truces (August, year-end) taken into account.

Guide

Frequently asked questions

Can works be carried out in August in Monaco?

Only quiet interior works are allowed in August. We therefore schedule demolition and noisy works outside this period.

How long does an apartment renovation take?

Allow 3 to 6 months for an apartment of 80 to 150 m², depending on the level of finish and whether a permit is required. Our estimator gives you a first idea.

Do I need an architect?

Yes, whenever the works require a DPUM permit: the application must be signed by an architect registered with the Monaco Order of Architects. We are happy to work with yours.

Why does renovating cost more in Monaco?

Labour, logistics (access, parking, removals), a restricted worksite calendar and the high standard of finishes explain a higher cost than elsewhere on the Riviera.

Who handles the formalities?

We prepare the formalities with the building manager and the administration together with you — and with your architect when a permit is required.

Sources: Princely Government, regulations on worksite noise and hours (ministerial orders of December 2018); Sovereign Ordinance no. 3.647 of 9 September 1966 on urban planning, construction and roads. General, non-contractual information: regulations may change, so we check them for every project.